§ 700.050. Uniform Standard For All Street Cuts To The Roads Within The City Limits.  


Latest version.
  • A. 
    Whenever at all possible, a road is never to be more than fifty percent (50%) blocked. If it is necessary to block more than fifty percent (50%) of the road for an extended period of time, it will be necessary to place barriers with the following information posted:
    1. 
    Precise location where the road is blocked and the approximate date the construction repairs will be completed;
    2. 
    Call Blue Springs R-IV School District bus service at 224-1385, and notify them of the road closure, including the precise location of the road block and the approximate date the construction repairs will be completed. A second call is to be made when the construction repairs arc definitely completed and the road is reopened.
    3. 
    Notify Central Jackson County Fire Protection District of the road closure, including the precise location of the road block and the approximate date the construction repairs will be completed. A second call is to be made when the construction repairs are definitely completed and the road is reopened.
    B. 
    For emergency repairs, such as for a broken water main, backfill aggregate AB-3 which is stored behind than maintenance building off of the lake road on the west side of the lake may be used.
    C. 
    All street cuts to the roads within the City of Lake Tapawingo, Missouri, owned and maintained by the Lake Tapawingo Development Company shall be repaired and maintained per Standard Drawing SR-1 dated February 17, 1998, attached hereto and detailed as followed:
    1. 
    Excavations shall be protected at all times. Cuts in the roadways shall be plated or temporarily filled with backfill aggregate when work is not being performed.
    2. 
    Backfill shall not be placed in water or mud. Clean graded rock or frozen material shall not be used as backfill. Backfill material shall consist of untreated compacted aggregate AB-3.
    3. 
    Roadway surfaces shall be similar to the existing roadway surface. All unsupported pavement shall be removed before beginning patch. All cuts shall be rectangular, with their dimensions parallel and perpendicular to the direction of traffic. Restoration shall be flush with adjoining surfaces. An identification tag shall fully identify the contractor performing the restoration and the date the restoration was made.
    4. 
    If the excavation is in asphalt and is within three (3) feet of an existing joint or cut or edge of the road, the surface shall be extended to that joint or cut. Tack coat shall be applied, surface placed and compacted and joints sealed.
    5. 
    Sidewalks, curbs and driveways and any section of which is cut shall be removed to within two (2) feet of the street repair or nearest joint, whichever is the closest. Restoration shall match existing surface material.
    6. 
    If the excavation requires the removal of any grass area, this area will be finished to grade with six (6) inches of topsoil compacted to ninety percent (90%) and topped with either seed or sod.
    7. 
    Any other areas, materials or surfaces not included herein which are disturbed during excavation shall be replaced as directed by the Lake Tapawingo Development Company Board.
    D. 
    Notifications of the following shall be required before actual excavation begins:
    1. 
    48-Hour minimum: MO ONE CALL 1-800-344-7483.
    2. 
    24-Hour minimum: City of Lake Tapawingo Missouri, Water and Sewer Maintenance Supervisor to mark water, sewer low pressure system lines and grinder pump electrical lines, CALL 816-719-3101.
    3. 
    The repair shall be maintained for three (3) years or for the bond period.
Ord. No. 786, 4-4-2000